Guide

Gravel by the Ton vs. the Cubic Yard: How Much to Order

At the density the JoistCalc gravel calculator uses for gravel and paver base, 105 pounds per cubic foot, one cubic yard weighs about 1.42 tons, so tons are roughly cubic yards × 1.42. A 10 × 20 ft driveway base 6 inches deep is 100 cubic feet: 3.7 cubic yards and 5.25 tons before waste, or 4.07 cubic yards and 5.78 tons to order once the calculator's default 10% waste factor is added. The rest of this guide shows where those numbers come from, how they change with the material, and how much a patio base, a walkway or a drain trench takes.


Why you measure in yards but buy in tons

The hole you are filling is a volume: length times width times depth. Many quarries and landscape yards, though, price aggregate by weight. Getting from one to the other takes a third number, the bulk density of the material, which is how many pounds one cubic foot of it weighs.

Density is not a fixed property of "gravel." It depends on the kind of rock, the size and shape of the pieces, how much fine material fills the gaps between them, and how much water the pile is holding. Water has weight, so a yard of material that has been rained on weighs more than the same yard dry, and when you buy by the ton you pay for that water. That is why the same cubic yard can be quoted at different tonnages by two suppliers, and why the calculator's own field note calls its densities approximate.

Two unit details matter. A cubic yard is 3 × 3 × 3 feet, which is 27 cubic feet. A ton in a US quote is normally the short ton of 2,000 lb, which is what the calculator uses. A metric tonne is 1,000 kg, about 1.1 short tons, so a quote in tonnes is roughly 10% heavier per unit than one in US tons. If you switch the calculator to Metric, its tonnage is shown in metric tonnes.

Volume (ft³) = Length (ft) × Width (ft) × Depth (in) ÷ 12 Cubic yards = Volume (ft³) ÷ 27 Tons per cubic yard = Density (lb/ft³) × 27 ÷ 2000 Tons to order = Volume (ft³) × Density × (1 + Waste %) ÷ 2000

Tons per cubic yard for each material in the calculator

These are the five densities built into the calculator's Material list, converted to tons per cubic yard. They are planning values, not test results for any particular quarry's product. To reproduce any row, enter Length 9 ft, Width 9 ft, Depth 4 in (exactly 27 cubic feet, one cubic yard), set Waste factor to 0 and pick the material: the tonnage shown is the figure in the last column.

Material optionDensityWeight of 1 yd³Tons per cubic yard
Gravel / paver base105 lb/ft³2,835 lb1.42
Crushed stone100 lb/ft³2,700 lb1.35
Sand100 lb/ft³2,700 lb1.35
Decorative / river rock95 lb/ft³2,565 lb1.28
Topsoil76 lb/ft³2,052 lb1.03

The spread is wider than it looks. For the same 10 × 20 ft area at 6 in with 10% waste, the order volume stays at 4.07 cubic yards whatever you pick, but the tonnage runs from 5.23 tons for river rock to 5.5 for crushed stone and 5.78 for paver base. If your supplier publishes a density or a tons-per-yard figure for the exact product, use theirs: divide their tons per yard by 27 and multiply by 2,000 to get pounds per cubic foot, which is a quick way to compare a quote against the table above.

Worked example: how many tons of gravel for a 10 × 20 driveway

A 10 ft × 20 ft parking pad with a 6 in base, using the calculator's Gravel / paver base option (105 lb/ft³) and its default 10% waste factor, in Imperial mode:

  1. Area = 10 × 20 = 200 sq ft
  2. Depth = 6 ÷ 12 = 0.5 ft
  3. Volume = 200 × 0.5 = 100 cu ft, which is 100 ÷ 27 = 3.7 cubic yards
  4. Order volume = (100 × 1.10) ÷ 27 = 4.07 cubic yards
  5. Weight = 100 × 105 × 1.10 = 11,550 lb = 5.78 tons
  6. Weight without waste = 10,500 lb = 5.25 tons

Enter Length 20, Width 10, Depth 6 and the calculator shows 5.78 tons, a volume of 100 ft³, an order volume of 4.07 yd³ and 5.25 tons without waste. The calculator opens with this same driveway at 4 in instead of 6, and pressing Calculate on its defaults gives 3.85 tons and 2.72 cubic yards: a third less material for a third less depth. That difference is why the depth decision, covered below, matters more than any rounding in the density.

Common jobs, run through the calculator

Every row below was computed with the calculator's own formula, in Imperial mode, with the default 10% waste factor. Type the inputs shown and you get the same results. The depths are the published minimums discussed in the next section, except the drain trench, whose size is only an example.

JobInputs (L × W × depth, material)VolumeOrder volumeTons, waste included
Paver driveway base, 1 car20 × 10 ft × 6 in, gravel / paver base100 ft³4.07 yd³5.78
Paver driveway base, long50 × 12 ft × 6 in, gravel / paver base300 ft³12.22 yd³17.33
Patio base, 12 × 1212 × 12 ft × 4 in, gravel / paver base48 ft³1.96 yd³2.77
Patio bedding sand, 12 × 1212 × 12 ft × 1 in, sand12 ft³0.49 yd³0.66
Paver walkway base30 × 3 ft × 4 in, gravel / paver base30 ft³1.22 yd³1.73
Drain trench (example size)50 × 1 ft × 12 in, crushed stone50 ft³2.04 yd³2.75

Two cautions on this table. First, the calculator counts the full trench, so for a drain with a pipe in it the stone figure is a little high by the volume the pipe takes up, which errs on the side of having enough. Second, the base depths are compacted minimums. Material with fines settles when it is compacted, so the loose depth you spread has to be greater than the finished depth; ask your supplier how much their product compacts and enter the loose depth, rather than adding it to the waste factor and losing track of both.

How much gravel for a patio base, walkway or driveway: the depth

For segmental paver work, the Concrete Masonry & Hardscapes Association (CMHA) publishes minimum base thicknesses in its tech note on constructing interlocking concrete pavements. They are minimums, stated for well-drained soil, and measured after compaction. The same note says colder climates and continually wet or weak soils need thicker bases.

UseMinimumConditionSource
Sidewalks, patios, pedestrian areas4 in baseAfter compaction, well-drained soilCMHA PAV-TEC-002
Residential driveway (pavers)6 in baseWell-drained soilCMHA PAV-TEC-002
Bedding sand under pavers1 inUncompacted nominal thickness, screededCMHA PAV-TEC-002
Cold climate, wet or weak soilThickerNo single figure given; local practice or an engineer decidesCMHA PAV-TEC-002

A plain gravel driveway with no pavers on top is not covered by that note, and there is no single national standard for one. The paver-driveway minimum is still a useful floor, since the base under a gravel surface carries the same cars. Where your soil is soft, wet, clay or subject to frost, plan on more depth than these minimums and check what local contractors or your county use.

Where gravel orders go wrong

Run your own numbers

The JoistCalc gravel calculator does every step above at once: enter length, width and depth, pick the material and waste factor, and it returns tons with waste, raw volume, order volume in cubic yards and tons without waste side by side, so a quote in either unit can be checked against the same job. It also switches to metric if your supplier works in meters and tonnes.

Where these numbers come from

The densities and every computed figure come from the calculator's own values and formula. The unit definitions and the base-depth minimums come from the sources below.

How many tons are in a cubic yard of gravel?

About 1.42 tons at the 105 lb/ft³ the calculator uses for gravel and paver base, and 1.35 tons for crushed stone at 100 lb/ft³. The exact figure depends on the product and its moisture, so use your supplier's number if they give one.

How many tons of gravel do I need for a 10x20 driveway?

At 6 inches deep with gravel or paver base and 10% waste, 5.78 tons (4.07 cubic yards). At 4 inches deep, 3.85 tons (2.72 cubic yards). Without any waste allowance the 6-inch figure is 5.25 tons.

How much gravel do I need for a 12x12 patio base?

At the 4-inch compacted minimum for patios, 2.77 tons (1.96 cubic yards) of paver base with 10% waste, plus 0.66 tons of bedding sand for a 1-inch layer. Spread the base loose a little deeper than 4 inches so it finishes at 4 after compaction.

How do I convert cubic yards of gravel to tons?

Multiply cubic yards by the density in lb/ft³, then by 27, then divide by 2,000. At 105 lb/ft³ that is cubic yards × 1.42; at 100 lb/ft³ it is cubic yards × 1.35.