Calculator 01 / Concrete

Concrete Calculator

Concrete is ordered by volume — length × width × thickness — so bag count depends on each bag's yield, not just the area you are covering. Figure cubic yards and bag count for slabs, footings, round columns, and stairs. Enter your measurements, pick a shape, and add a waste buffer before you order.


Covers spillage, uneven subgrade, and form overage. 5–10% is typical.

How this calculator works

Concrete volume is length × width × thickness, converted to cubic feet and then to cubic yards (concrete is sold by the cubic yard for ready-mix, or by the bag for small pours). This tool applies the same formulas ready-mix suppliers and bagged-mix manufacturers use:

Slab / footing: Volume (ft³) = Length (ft) × Width (ft) × (Thickness (in) ÷ 12) Round column: Volume (ft³) = π × (Diameter (in) ÷ 24)² × Height (ft) Stairs: Volume (ft³) = [N × (N + 1) ÷ 2] × Riser (ft) × Tread (ft) × Width (ft) Cubic yards: Cubic yards = Volume (ft³) ÷ 27 Bags needed: Bags = [Volume (ft³) × (1 + Waste %)] ÷ Bag yield (ft³)

The stairs formula treats each step as a stacked rectangular block, which is the standard approximation used for a solid stair pour (no separate stringer or void beneath).

Worked example: a 20 × 10 ft slab

A 20 ft × 10 ft patio slab at 4 in thick, 10% waste, priced in 60 lb bags:

  1. Volume = 20 × 10 × (4 ÷ 12) = 66.7 cu ft
  2. With 10% waste = 73.3 cu ft
  3. Cubic yards = 73.3 ÷ 27 = 2.72 yd³
  4. Bags = 73.3 ÷ 0.45 = 163 bags

That bag figure is the useful part of this example. A hundred and sixty-three 60 lb bags is nearly five tons of material to carry, open and mix, and every one of them has to be mixed to the same consistency or the slab cures unevenly. At 2.7 cubic yards this is firmly a ready-mix job. Bagged concrete stops making sense somewhere around a cubic yard — roughly 45 to 90 bags depending on size — and that threshold arrives far sooner than most people expect.

Bags, yields and when to stop bagging

Bag yield is the finished volume one bag produces, not the weight of the powder. It is printed on the sack, and these are the standard figures.

BagYieldBags per cubic yard
40 lb0.30 ft³90
60 lb0.45 ft³60
80 lb0.60 ft³45

Ready-mix has its own arithmetic. Suppliers generally have a minimum load and charge a short-load fee below a few cubic yards, so a small pour can cost more per yard than a large one — worth a phone call before deciding, because the crossover point is a price question, not just a volume one.

Typical slab thickness

Thickness is a structural decision that belongs to your plans and your local code, not to a table on a website. These are the common starting points, and every one of them assumes a properly prepared and compacted base beneath.

PourCommon thicknessNotes
Walkway or patio4"Foot traffic only
Residential driveway4–6"Thicker where vehicles turn
Garage floor4–6"6" if anything heavy is stored
Shed or workshop base4"Thicken the edge as a perimeter beam
Heavy vehicle or equipment6–8"+Engineered, with reinforcement designed for it

For footings, use the slab tab — a strip footing is simply a long, narrow slab, and a pad footing is a short one. Footing size and depth are structural and frost-related, and they must come from your plans, an engineer, or the local frost-depth requirement rather than from a general table.

Where concrete orders go wrong

  • Ordering exactly what the maths says. Concrete has no second chances — a pour that runs short mid-slab leaves a cold joint you cannot undo. The waste factor exists for uneven subgrade, over-dig and spillage, and subgrade is almost never as flat as it looks.
  • Forgetting the base settles. A slab poured on soft or uncompacted fill uses more concrete than its nominal thickness, because the wet weight pushes down into it.
  • Bagging a job that wants ready-mix. See above. Beyond about a cubic yard, bags cost more in labour and time than the delivery saves, and consistency suffers.
  • Ignoring the pour window. Volume says nothing about whether you can place and finish it before it goes off. Hot, dry or windy conditions shorten that window considerably.
  • Leaving out reinforcement and control joints. Neither shows up in a volume calculation, and both determine whether the slab cracks where you chose or where it likes.

Where these numbers come from

Yield, slump and curing all move the number of bags or yards you actually need. These are the bodies that publish the underlying guidance.

How much waste factor should I add?

5–10% covers most slab pours. Add more (10–15%) for uneven or unexcavated subgrade, hand-dug footings, or irregular forms where over-digging is likely.

When should I order ready-mix instead of bags?

As a rule of thumb, pours over roughly 1 cubic yard (about 60–70 bags of 60 lb mix) are usually cheaper and faster with a ready-mix delivery than hand-mixing bags.

Does this account for rebar or wire mesh volume?

No — reinforcement takes up a negligible fraction of pour volume and is not subtracted. This calculator estimates gross concrete volume only.

Can I save, share, or print a calculation?

Yes — use the Save, Copy link, and Print buttons under your results. Saved calculations can be grouped into a named project on the My Projects page for a combined job estimate with cost totals. Everything is stored only in your browser, never uploaded — see the Privacy Policy for details.

Estimates only. Confirm final quantities with your ready-mix supplier or bagged-mix manufacturer, and always order slightly more than the calculated minimum.