Guide

How Many Bags of Concrete Make a Cubic Yard, and When to Order Ready-Mix

One cubic yard of concrete takes 90 bags of 40 lb mix, 60 bags of 60 lb mix or 45 bags of 80 lb mix, before you add anything for waste. This guide shows where those figures come from, works through a slab, a run of fence posts and a set of pad footings, and lays out the arithmetic for deciding when a ready-mix truck beats a pallet of bags.


Bags per cubic yard: the short answer

A bag of concrete mix is sold by weight but used by volume. What matters is its yield: the volume of finished concrete one bag makes once water is added. A cubic yard is 27 cubic feet, so bags per yard is simply 27 divided by the yield. The yields below are the ones the concrete calculator uses, and they match the approximate yields Quikrete publishes on its Concrete Mix data sheet.

BagYield per bagBags per cubic yard (no waste)Dry mix per cubic yard
40 lb0.30 ft³903,600 lb
60 lb0.45 ft³603,600 lb
80 lb0.60 ft³453,600 lb

To reproduce the bag column in the concrete calculator, use the Slab / Footing tab with length 27 ft, width 1 ft, thickness 12 in, one slab, waste factor 0%, and switch the bag size. The last column is just bags × bag weight, and it is the same 3,600 lb whichever size you buy: smaller bags do not mean less lifting, only more trips. The same data sheet also lists 50 lb (0.375 ft³) and 90 lb (0.675 ft³) bags, which work out to 72 and 40 bags per yard; the calculator's bag selector does not offer those two sizes, so divide by their yield yourself. Fast-setting and specialty mixes have their own yields, which is another reason to read the bag.

Worked example: a 10 × 10 ft slab at 4 in

This is the calculator's default input: Slab / Footing tab, 10 ft × 10 ft, 4 in thick, one slab, 10% waste.

  1. Volume = 10 × 10 × (4 ÷ 12) = 33.3 ft³
  2. With 10% waste = 36.7 ft³
  3. Cubic yards = 36.7 ÷ 27 = 1.36 yd³
  4. Bags, rounded up: 123 × 40 lb, 82 × 60 lb, or 62 × 80 lb

Sixty-two 80 lb bags is 4,960 lb of dry mix to unload, carry, open, mix and place, and it all has to go in before the first batches set. Quikrete's data sheet asks for 6 to 9 pints of water per 80 lb bag and at least 1 ft³ of mixer capacity for each 80 lb bag mixed at once, so the size of your mixer sets how many separate batches this slab becomes.

Worked example: ten fence-post holes

Quikrete's fence-post instructions suggest a hole about three times the post's diameter, dug to one-third of the post's overall height. For a 4×4 (actually 3½ in square) that is roughly a 10 in hole, and for a 9 ft post a 3 ft depth. In the calculator, use the Round Column tab: diameter 10 in, height 3 ft, 10 columns, 10% waste. It returns 16.4 ft³ before waste, 18 ft³ with it, 0.67 yd³, and 60 × 40 lb, 40 × 60 lb or 30 × 80 lb bags.

One thing to know: the calculator treats each hole as solid concrete and does not subtract the post. A 3½ in square post standing 3 ft deep takes up about 0.26 cubic feet per hole, or about 2.6 cubic feet across ten holes, which is a little over four 80 lb bags. On post jobs that difference simply becomes extra margin, which is useful, because hand-dug holes are rarely as neat as the number you typed in.

Worked example: a set of pad footings

A pad footing is a short, thick slab, so it goes in the Slab / Footing tab. Take eight pads, each 2 ft × 2 ft × 12 in deep, at 10% waste (enter length 2, width 2, thickness 12, number of identical footings 8). The calculator returns 32 ft³ before waste, 35.2 ft³ with it, 1.3 yd³, and 118 × 40 lb, 79 × 60 lb or 59 × 80 lb bags. These dimensions are only an example of the arithmetic. Real footing sizes and depths are structural and frost-related, and must come from your plans, an engineer or your local code.

Bags or ready-mix: where the crossover sits

All three examples above land between about two-thirds of a yard and a yard and a half, which is exactly the range where the decision is genuinely close. The calculator page's rule of thumb is about one cubic yard. Rather than trust any single number, weigh these four things against your own job.

You can find your own crossover with two quotes and no guesswork. Price both options for the same volume, including the waste allowance:

Bagged cost: Bags (from the calculator) × price per bag Ready-mix cost: Cubic yards ordered × price per yard + any delivery or small-load charge

Then add what the price comparison leaves out: mixer rental, an extra pair of hands, and whether the truck can actually reach the forms. NRMCA points out that a loaded concrete truck weighs about 80,000 lb and may not be able to cross loose dirt or residential curbs, so a backyard pour may also need a pump or wheelbarrows, which changes the comparison again.

Thickness drives everything, so get it from a source

Volume rises in direct proportion to thickness, so a 6 in slab takes half again as much concrete as a 4 in one. Manufacturer guidance gives these common starting points; your plans and local code take precedence.

PourThicknessSource
Patio4 in, generallyQuikrete, Concrete Patios
Driveway, passenger cars only4 inQuikrete, Concrete Driveways and Curbs
Driveway used by trucks or heavy vehicles5 to 6 inQuikrete, Concrete Driveways and Curbs
Minimum pour with Quikrete Concrete Mix2 inQuikrete Concrete Mix data sheet

For comparison, the same 10 × 10 ft slab at 6 in instead of 4 in comes out at 2.04 yd³ and 92 × 80 lb bags with 10% waste, which moves it from borderline to a clear ready-mix job.

Where concrete estimates go wrong

Where these numbers come from

Bag yields, mixing water and thickness guidance come from the manufacturer's published documents; ordering margins, truck capacity and yield problems come from the ready-mix industry's own technical notes. Every bag count and volume on this page was produced by this site's concrete calculator with the inputs stated beside it.

How many 80 lb bags of concrete do I need for a 10 × 10 slab?

At 4 in thick with 10% waste, 62 bags. Without any waste allowance it would be 56, which is why the waste factor matters. At 6 in thick with 10% waste, it is 92 bags.

Is it cheaper to buy 40 lb or 80 lb bags?

Compare price per cubic foot, not price per bag: divide the bag price by its yield (0.30 ft³ for 40 lb, 0.60 ft³ for 80 lb). The amount of dry mix per cubic yard is the same either way, so the choice is about price and how much weight you want to lift at once.

How many cubic yards does a ready-mix truck carry?

NRMCA gives truck mixer capacity as 8 to 12 cubic yards, so a typical home pour fills only part of one. Ask your supplier about minimum orders and small-load charges before you compare prices.